Guide11 min read
How to Reduce Changeover Time in Manufacturing (SMED)
Cut changeover time with SMED: move set-up work outside the machine stop, simplify what stays inside, then standardise it. Steps, example and checklist.
By Occulax team

On this page
- What is changeover time?
- What is the full form of SMED?
- Internal vs external activities: what is the difference?
- How to reduce changeover time: the SMED steps
- Worked example: a press changeover before and after SMED
- Changeover reduction checklist
- How do you measure changeover time?
- Measuring changeovers with the cameras you already have
- Frequently asked questions
Every time a press, moulding machine or CNC switches from one part to the next, it stops making money. In many plants that changeover time is the single largest planned loss on the shift, yet it is rarely timed, rarely written down and almost never treated as something that can be engineered. This guide explains what changeover time is, what SMED means, and how to cut changeovers step by step on your own shop floor.
Quick answer To reduce changeover time, use SMED: record a real changeover, split every task into internal (machine must be stopped) and external (can be done while it runs), move as much as possible to external, then simplify the internal tasks that remain with quick clamps, standard heights and fixed settings. Standardise the new method and time every changeover so it stays short.
What is changeover time?
Changeover time is the time from the last good part of the previous run to the first good part of the next run, at normal speed and quality. It includes waiting for tools, hunting for bolts, cleaning, adjustments, trial shots and first-piece approval — not just the tool swap.
That definition matters. Many plants record only the "tool change" and miss the 20 minutes of trial and adjustment after it. If the machine is not producing good parts at rate, the changeover is not over.
In OEE terms, changeover is an availability loss: it is time the machine was planned to run but did not. If you track OEE, changeovers usually show up as one of the biggest slices of lost time. See how to calculate OEE for how this fits into the full calculation.
A simple way to see how much it costs you:
Changeover loss % = total changeover minutes ÷ planned production minutes × 100
Example A machine runs a 480-minute shift and has two changeovers of 45 minutes each. Changeover loss = 90 ÷ 480 × 100 = 18.75% of the shift. Nearly one hour in five is spent not making parts.
What is the full form of SMED?
SMED stands for Single-Minute Exchange of Die. "Single-minute" means a single-digit number of minutes — under 10 — not literally one minute. The method was developed by the Japanese engineer Shigeo Shingo, who worked with Toyota among others, and is described in his book A Revolution in Manufacturing: The SMED System.
Despite the name, SMED applies to any changeover: moulds, fixtures, cutting tools, colours on a paint line or sizes on a packing machine.
The core idea is simple. Most changeovers are slow not because the technical work is hard, but because work that could be done while the machine is running is done while it is stopped.
Internal vs external activities: what is the difference?
| Type | Definition | Examples |
|---|---|---|
| Internal | Can only be done while the machine is stopped | Unclamping the old die, fixing the new die, setting the stroke, trial run |
| External | Can be done while the machine is still running the previous job | Fetching the next die, collecting tools and bolts, pre-heating a mould, preparing material, filling paperwork |
The whole SMED method rests on this split. Internal time is the changeover time. External time is work that still has to happen, but it costs no machine time if it is finished before the machine stops.
Note The same task can be internal in one plant and external in another. Pre-heating a mould is internal if you do it on the machine and external if you do it on a heating station beforehand. SMED is about deliberately moving tasks from the first column to the second.
How to reduce changeover time: the SMED steps
Step 1: Observe and record a real changeover
Pick one machine with frequent or long changeovers. Record a full changeover, last good part to first good part, ideally on video with a stopwatch log of every task: who did what, where they walked, what they waited for.
The recording, not what the changeover "normally" takes, is your baseline.
Step 2: Separate internal and external tasks
With the operators and setters, mark every task as internal or external. You will usually find a large share of "internal" time is really external work done at the wrong moment: walking to the tool room, searching for the right spanner, waiting for the crane, waiting for material.
Doing that work before the machine stops often gives the first big cut, at no cost.
Step 3: Convert internal tasks to external
Now look at the tasks that really are internal and ask: could part of this be done in advance?
- Pre-set tools and fixtures off the machine.
- Pre-heat moulds or dies on a separate station.
- Keep the next die cleaned, checked and staged next to the machine.
- Prepare a changeover trolley with exactly the tools, bolts and gauges needed.
Step 4: Streamline the remaining internal tasks
What is left must be done with the machine stopped, so make it fast:
- Quick-release clamps instead of loose bolts and nuts.
- Standard die or mould heights and locating pins so the tool drops into position.
- Eliminate adjustments: record the correct settings for each part and set them directly, rather than trial and error.
- Parallel working: two people working on both sides of the machine at once, with a clear sequence.
- One-turn fasteners or fewer bolts where safety allows.
Adjustments and trial runs are often the largest single chunk. A settings sheet per part and a quick first-off check can remove most of them.
Step 5: Streamline external tasks
If external tasks are late, the machine waits. Store dies near the point of use, label racks clearly and plan the next changeover in the shift schedule so material and tools are ready.
Step 6: Standardise and repeat
Write the new method as a one-page changeover standard with the sequence, who does what and target time. Train every shift on it. Then pick the next machine and repeat. SMED is a cycle, not a one-off project.
Worked example: a press changeover before and after SMED
The table below is an illustrative example of a die change on a mechanical press. Times are in minutes of machine stoppage (internal time).
| Activity | Before (min) | After (min) | What changed |
|---|---|---|---|
| Fetch next die from store | 15 | 0 | Die staged next to the press before the stop (external) |
| Find tools, clamps and bolts | 10 | 0 | Changeover trolley prepared in advance (external) |
| Unclamp and remove old die | 12 | 6 | Quick-release clamps |
| Clean press bed and new die | 8 | 4 | New die cleaned in advance; only the bed cleaned during the stop |
| Position and clamp new die | 15 | 6 | Locating pins and standard die height |
| Adjust shut height and shims | 12 | 3 | Settings recorded per die; shims eliminated |
| Trial strokes and first-piece approval | 18 | 8 | Fixed settings, first-off gauge kept at the press |
| Total internal time | 90 | 27 | 63 minutes saved (70%) |
The work moved to external — fetching the die (15 min), preparing tools (10 min) and pre-cleaning the die (4 min) — still takes 29 minutes, but it is done while the press is running the previous job.
If this press has three changeovers a day, the saving is 3 × 63 = 189 minutes a day. Over 300 working days that is 56,700 minutes, or 945 hours of press time returned to production — without buying a new machine.
Tip Shorter changeovers also let you run smaller batches. That cuts work-in-progress and finished stock, and makes it easier to match production to orders.
Changeover reduction checklist
Use this checklist when you run a SMED exercise on a machine:
| Check | Yes / No |
|---|---|
| Changeover is defined as last good part to first good part | |
| A real changeover has been recorded and timed task by task | |
| Every task is marked internal or external | |
| Next die, mould or fixture is staged at the machine before the stop | |
| A changeover trolley or kit holds every tool, bolt and gauge needed | |
| Material for the next job is at the machine before the stop | |
| Settings for each part are recorded and set directly | |
| Quick clamps or standard heights used where possible | |
| Two-person parallel sequence defined for long changeovers | |
| First-piece approval can be done at the machine without waiting | |
| One-page changeover standard is displayed at the machine | |
| Every changeover is timed and reviewed weekly |
How do you measure changeover time?
You cannot improve what you do not measure consistently. For each changeover, record:
- Start: time of the last good part of the previous job.
- End: time of the first good part of the new job at normal speed.
- Machine, part going out, part coming in, shift and the team who did it.
Then review weekly:
- Average changeover time per machine and per product pair.
- Spread: the gap between the fastest and slowest changeovers. A wide spread usually means the method is not standardised.
- Number of changeovers per shift.
- Changeover loss % of planned production time, using the formula above.
Handwritten logs tend to round times and miss the trial period. If changeovers are a constraint at your bottleneck machine, every minute there is lost output for the whole plant — see how to identify bottlenecks in production. Changeover is also closely related to other stoppages; the methods in how to reduce machine downtime apply to unplanned stops in the same way.
Good housekeeping helps too. A changeover trolley only works if tools go back to their place, which is what 5S in the factory is about.
Measuring changeovers with the cameras you already have
Most factories already have CCTV cameras looking at their machines. OCCULAX connects to those existing RTSP/NVR streams — no new hardware — and finds when machines stop and how much machine time is lost. It learns each factory's operating patterns and standard cycle baselines, and rolls machine uptime, people, flow, quality, safety and housekeeping into one Factory Health Score on your phone, with the rupee impact of the losses and the areas to improve.
For changeovers, that means you can see how long machines are actually stopped, rather than relying on a log written at the end of the shift. Video stays on-premise through a local gateway, with no external video storage. You can read more on how it works or in the FAQ.
Frequently asked questions
What is changeover time in manufacturing?
Changeover time is the time from the last good part of one production run to the first good part of the next, at normal speed and quality. It includes tool changes, cleaning, adjustments, trial runs and first-piece approval.
What is the full form of SMED?
SMED stands for Single-Minute Exchange of Die. It is a method developed by Shigeo Shingo to bring changeovers down to a single-digit number of minutes, mainly by moving work outside the machine stop.
What is the difference between internal and external set-up?
Internal set-up is work that can only be done while the machine is stopped, such as clamping a new die. External set-up can be done while the machine is still running, such as fetching the next die or preparing tools.
How can I reduce changeover time quickly?
Start by doing all external work before the machine stops: stage the next tool, material and a full tool kit at the machine. Then record settings for each part so adjustments and trial runs are cut down.
Is changeover time included in OEE?
Yes. Changeover time is planned production time in which the machine does not produce, so it reduces availability in the OEE calculation. Treating it as a planned stop hides one of the biggest improvement opportunities.
How often should changeover time be measured?
Every changeover should be timed from last good part to first good part, and the results reviewed weekly by machine and product pair. Consistent measurement is what keeps a SMED improvement from slipping back.
Want to see where machine time really goes in your plant? Start a 14-day pilot with the cameras you already have.
- Lean manufacturing
- SMED
- Changeover time
- OEE
- Set-up reduction