How to Reduce Rejection Rate in Manufacturing (With Formula)
Rejection rate = rejected ÷ total produced × 100. Formula, PPM, first-pass yield, rework vs scrap, root-cause tools and a step-by-step plan to cut rejection.
By Occulax team

On this page
- What is the rejection rate formula?
- What is the difference between rework and scrap?
- Worked example: rejection rate, PPM and first-pass yield
- What causes rejection in production?
- Which root-cause tools should you use?
- How to reduce rejection rate: a step-by-step plan
- Spotting rejection patterns with the cameras you already have
- Frequently asked questions
Rejection is one of the most expensive losses in a factory because you pay for it twice: once for the material, machine time and labour that went into the bad part, and again for the inspection, rework or replacement that follows. Yet in many plants the rejection rate is a monthly number in a quality report that nobody on the floor sees. This guide explains how to calculate rejection rate, PPM and first-pass yield, the difference between rework and scrap, the root-cause tools that work, and a step-by-step plan to reduce rejection in production.
Quick answer Rejection rate (%) = rejected units ÷ total units produced × 100. To reduce it, measure it the same way on every shift, sort rejects by defect type and machine, use a Pareto chart to pick the top one or two defects, find their root cause with 5 Whys or a fishbone diagram, fix the cause (not the symptom), and lock the fix into the standard so it stays fixed.
What is the rejection rate formula?
The standard formula is:
Rejection rate (%) = Rejected units ÷ Total units produced × 100
Count rejects at the same point every time — for example, at final inspection — and use the total produced for the same period, machine or line.
These related measures are worth tracking alongside it:
| Measure | Formula | What it tells you |
|---|---|---|
| Rejection rate | Rejected ÷ Total produced × 100 | Share of output that failed inspection |
| PPM (parts per million) | Rejected ÷ Total produced × 1,000,000 | Same thing on a finer scale; used when rejection is low and by most OEM customers |
| First-pass yield (FPY) | Units good first time, without rework ÷ Units started × 100 | Share made right first time |
| Scrap rate | Scrapped ÷ Total produced × 100 | Share that was lost completely |
PPM is just the rejection rate multiplied by 10,000. A 0.5% rejection rate is 5,000 PPM. Customers who measure suppliers in PPM usually count parts they reject at their end, so your internal PPM and customer PPM are separate numbers. Track both.
What is the difference between rework and scrap?
- Rework is a defective part that can be corrected — deburred, re-machined, re-welded, repainted — and then passes inspection.
- Scrap is a defective part that cannot be corrected and is thrown away or sold as scrap.
Both count as rejects at first inspection. Rework looks cheaper because the part is saved, but it still costs labour, machine time and often a second inspection, and it delays the order. A plant that "has low scrap" can still have a serious rework problem, which is why first-pass yield matters more than final yield.
Note If reworked parts are counted as good and the rejection rate is calculated only on scrap, the number will look much better than the process really is. Count rejects at first inspection, before rework.
Worked example: rejection rate, PPM and first-pass yield
An illustrative example for a component line in one month:
| Item | Quantity |
|---|---|
| Total parts produced | 50,000 |
| Rejected at first inspection | 1,500 |
| — of which reworked and passed | 1,000 |
| — of which scrapped | 500 |
| Good first time | 48,500 |
| Good after rework | 49,500 |
Now the measures:
| Measure | Calculation | Result |
|---|---|---|
| Rejection rate | 1,500 ÷ 50,000 × 100 | 3.0% |
| Rejection PPM | 1,500 ÷ 50,000 × 1,000,000 | 30,000 PPM |
| First-pass yield | 48,500 ÷ 50,000 × 100 | 97.0% |
| Final yield (after rework) | 49,500 ÷ 50,000 × 100 | 99.0% |
| Scrap rate | 500 ÷ 50,000 × 100 | 1.0% |
The final yield of 99% looks fine. The first-pass yield of 97% shows that 1,500 parts a month needed extra handling.
If scrapped parts cost ₹40 each in material and processing, and each rework costs ₹6 in labour and machine time (illustrative figures), the monthly cost is 500 × ₹40 = ₹20,000 in scrap plus 1,000 × ₹6 = ₹6,000 in rework — ₹26,000 a month, before counting inspection time and delays. See manufacturing cost per unit for how this raises the cost of every good part.
Tip On a line with several operations, multiply the first-pass yield of each step to get rolled throughput yield. Three steps at 98%, 97% and 99% give 0.98 × 0.97 × 0.99 ≈ 94.1% — lower than any single step.
What causes rejection in production?
Most rejection traces back to a handful of sources. The classic way to group them is the 6M used in a fishbone diagram:
| Category | Typical causes |
|---|---|
| Man (people) | Untrained operator, no work instruction, fatigue, skipped step |
| Machine | Worn tooling, wrong settings, vibration, poor maintenance |
| Method | No standard method, settings changed between shifts, weak first-piece check |
| Material | Out-of-spec raw material, mixed batches, damage in handling |
| Measurement | Gauge not calibrated, different gauges used, unclear acceptance criteria |
| Mother nature (environment) | Temperature, humidity, dust, poor lighting at inspection |
Rejection also clusters around particular moments: the first parts after a changeover, the start of a shift, a new operator, a new batch of material. Note when rejects happen, not only how many — see how to reduce changeover time.
Which root-cause tools should you use?
Pareto analysis. Sort rejects by defect type and count them. Usually a few defect types make up most of the rejects. Work on those first.
An illustrative Pareto for the 1,500 rejects above:
| Defect type | Count | % of rejects | Cumulative % |
|---|---|---|---|
| Burr | 600 | 40% | 40% |
| Dimension out of tolerance | 375 | 25% | 65% |
| Dent or scratch | 270 | 18% | 83% |
| Missing operation | 150 | 10% | 93% |
| Others | 105 | 7% | 100% |
| Total | 1,500 | 100% |
Fixing burrs and dimensional defects addresses 65% of rejection.
5 Whys. Ask "why?" repeatedly until you reach a cause you can act on:
- Why are parts rejected? Burrs on the edge.
- Why are there burrs? The cutting tool is worn.
- Why was a worn tool in use? It is changed only when the operator notices burrs.
- Why only then? There is no tool-life limit.
- Why no limit? Tool life was never defined in the standard.
Fix: set a tool-change interval by part count and add it to the work standard.
Fishbone (Ishikawa) diagram. When the cause is not obvious, the team lists possible causes under each of the 6M headings, then checks the most likely ones with data.
How to reduce rejection rate: a step-by-step plan
- Define it consistently. Decide where rejects are counted (first inspection, before rework) and use the same formula on every shift and line.
- Record by type, machine and shift. A single total tells you nothing about what to fix. A simple tally sheet at each inspection point is enough to start.
- Run a Pareto. Pick the top one or two defect types. Do not try to fix everything at once.
- Find the root cause. Go to the machine, look at the defective parts, and use 5 Whys or a fishbone with the operators.
- Fix the cause, not the symptom. Adding inspection catches defects; it does not stop them. Prefer fixes such as tool-life limits, recorded machine settings, fixtures that only fit one way, and error-proofing (poka-yoke).
- Strengthen the first-piece check. Approve the first part after every changeover, tool change and shift start before running the batch.
- Verify with data. Compare the rejection rate for that defect before and after for several weeks.
- Standardise. Update the work instruction, control plan and training so the fix survives a change of operator.
- Move to the next defect. Rejection reduction is a cycle, like SMED and 5S.
Housekeeping plays a part too: mixed bins, unlabelled material and dirty inspection areas cause avoidable rejects. See 5S housekeeping in the factory. Quality is also one of the three parts of OEE — see how to calculate OEE.
Spotting rejection patterns with the cameras you already have
Gauges, CMMs and inspection remain the way to measure dimensions and internal defects — cameras cannot do that. What existing CCTV can show is what is visible on the floor. OCCULAX connects to a factory's existing RTSP/NVR streams, with no new hardware, and one of its six factory vitals is quality: visible rejection patterns. Alongside machine uptime, people, flow, safety and housekeeping, this feeds one Factory Health Score on your phone, with the rupee impact and the areas to improve.
That helps link rejects to what else was happening — stops, waiting, changeovers — when they occurred. Video stays on-premise through a local gateway, with no external video storage. See how it works or the FAQ.
Frequently asked questions
How do you calculate rejection rate in manufacturing?
Divide the number of rejected units by the total units produced in the same period and multiply by 100. For example, 1,500 rejects out of 50,000 parts is a 3% rejection rate.
How do you convert rejection rate to PPM?
Divide rejects by total produced and multiply by 1,000,000, or simply multiply the percentage by 10,000. A 3% rejection rate is 30,000 PPM.
What is first-pass yield?
First-pass yield is the percentage of units that pass inspection the first time, without rework. It is calculated as good-first-time units ÷ units started × 100.
How can I reduce rejection in production quickly?
Run a Pareto of last month's rejects by defect type, pick the largest one, and find its root cause at the machine with the operators. A tighter first-piece check after every changeover and tool change often gives fast results.
Is rework counted in the rejection rate?
It should be. Count every part that fails first inspection as a reject, whether it is later reworked or scrapped. Counting only scrap makes the rejection rate look better than the process really is.
What is a good rejection rate?
There is no single figure; it depends on the product, process and customer. Many automotive and OEM customers set PPM targets in their supplier agreements, so use your customer's target and your own trend as the benchmark.
To see visible quality patterns alongside machine time and flow in your plant, start a 14-day pilot with the cameras you already have.
- Lean manufacturing
- Rejection rate
- Quality control
- Root cause analysis
- First-pass yield